
Chapter 18: Other accounting standards
© EWP Go to www.emilewoolfpublishing.com for Q/As, Notes & Study Guides 475
The gross amount due from customers or the gross amount due to customers for
contract work. This is calculated as follows:
$ $
Costs incurred X X
Plus recognised profits to date/(or minus recognised losses) X/(X) X/(X)
Minus progress billings (X) (X)
–––
= Inventories: Due from customers on contracts
X
––––
Non-current liabilities: Due to customers on contracts
––––
(X)
–––
(Note: ‘Progress billings’ are the amounts that the customer has been invoiced
already, during the progress of the contract to date.)
Note the calculations carefully: (1) Costs incurred (2) plus profits taken to date (3)
minus amounts billed to the customer (4) equals inventory in the statement of
financial position.
Receivables may also include amounts recoverable on contracts where progress
billings exceed cash received from the customer. This amount may include
retentions, disclosed above. For example, if progress billings have been $3 million
but the customer has paid only $2.5 million of the amounts billed, there will be a
receivable for $0.5 million in the statement of financial position, for ‘amounts
recoverable on contracts’.
Example
A construction contractor has a fixed price contract for $9,000 to build a bridge. The
initial amount of revenue agreed in the contract is $9,000. The contractor’s initial
estimate of contract costs is $8,000. It will take three years to build the bridge.
By the end of year 1, costs incurred were $2,093 and the anticipated costs to
complete the project were $5,957.
In year 2, costs incurred to date were $6,168 and the estimated total costs had risen
to $8,200. As a result the customer approves a variation in the contract revenue to
cover the over-run on costs (the excess costs above the original estimate). This
results in an increase in contract revenue of $200.
At the end of year 2, costs incurred include $100 for standard material stored at the
site. This material will be used in year 3 to complete the project.
The contract is completed in year 3, and the final costs incurred were $8,200.
Payments were made in stages. An advance payment of $2,500 was made at the start
of year 1. A progress payment of $4,000 was made in Year 2. The final payment
(including the $200 variation) was made at the end of year 3.