
//INTEGRAS/KCG/P AGIN ATION/ WILEY /WPS /FINALS_1 4-12- 04/0470855088_ 16_CHA15 .3D – 334 – [331–348/18]
20.12.2004 7:47PM
where the wind turbines are connected and describe the overall electrical design of the
grid connections of the wind turbines. Referring to the characteristics of grids and wind
turbines, I will describe the impact of the wind turbi nes on power quality, on the one
hand, and the effect that the power quality has on the wind turbines, on the other hand.
15.2 Network Characteristics
This section summarises the main characteristics of the Indian grids, which are important
with regard to the interrelationship between wind turbines and grids. I will focus on the grid
in the Muppandal region, where more than half of the wind turbines in Tamil Nadu are
connected. In addition, the grid in the coastal region around Lamba in Gujarat is described.
15.2.1 Transmission capacity
One of the most critical issues for the development of wind energy in India has been the
transmission capacity of the grid in the areas where the wind farms were built. Similar to
many other countries, wind farms are concentrated in rural areas, where the existing
transmission grids are very weak. In addition, in India the new wind farms were built
during a comparatively short period of time and were restricted to a few areas, and the
reinforcement of the transmission system in these areas has lagged behind the fast
development of wind energy.
In Tamil Nadu, almost 600 MW of wind energy were inst alled over the three- year
period from 1994 to 1997. Approximately 400 MW of the wind energy capacity are
located in the Muppandal area. Figure 15.2 shows the grid connection diagram for that
area. The 110 kV Arumuganeri–Kodayar ring mains was constructed to supply the
Muppandal area with power. The capacity of the ring mains itself is only 200 MVA.
To improve transmission capacity, an additional 110 kV line to Melak Kalloor and two
230 kV lines from the S. R. Pudur substation to the Tutucorin 230/110 kV substation
and the Kayathar 230/110/11 kV substation, respectively, have now been installed as a
supplement to the ring mains.
Figure 15.2 indicates the sho rt-circuit levels at selected points of the 110 kV and
230 kV grid. The short-circuit power at the wind farm substations of the 110 kV ring
mains is about 800 MVA. This is very low considering that approximately 200 MVA of
wind power are connected directly to the ring.
In Gujarat, there are 60 MW of wind power capacity in the coastal area around
Lamba. The wind farms are connected to three dedicated substations, as shown in
Figure 15.3. The power from the wind farms is evacuated through a 66 kV line with a
capacity of 30 MVA, and a 132 kV double line with a total capacity of 60 MVA.
In June 1998, the capacity installed at these substations amounted to 75 MW. However,
in June 1998, a capacity of approximately 40 MW was damaged by a cyclone, which also
damaged the overhead lines that were used for the transmission of the power from the
wind farms. Before the cyclone, the only transmission line was a 66 kV line with a capacity
of 30 MVA. This configuration led to grid outages as a result of load shedding and grid
breakdowns after a 66 kV conductor snapped because of age and overloading. The process
of ageing of the line has been accelerated by the saline atmosphere close to the sea.
334 Wind Farms in Weak Power Networks in India