FIRST YEAR OF OPERATION
UPPER LIMIT FOR POWER GENERATION - 5000 PPM
ALL RUNNER (EXCEPT 2, WITH PLASMA NITRIDING) AND
ALL OTHER UNDER WATER PARTS WERE UNCOATED
HEAVY DAMAGE AT THE END OF MONSOON SEASON TO ALL
RUNNERS, GUIDE VANES, CHEEK PLATES AND LABYRINTH
SEALS REGARDLESS OF PLASMA COATING
SECOND YEAR OF OPERATION
ALL UNITS REFURBISHED (DURING SEP-2004 TO APRIL-2005)
IN VIEW OF FAILURE OF PLASMA COATING, HVOF TYPE
TUNGSTON CARBIDE COATING PROVIDED TO SOME
COMPONENTS IN UNIT 4, 5 & 6
PERFORMANCE OF UNIT 5 AND 6 WITH REFERENCE TO SILT
LOAD WAS MUCH BETTER BECAUSE THE UPPER AND
LOWER CHEEK PLATES, GUIDE VANES, SEALING RING WERE
EITHER COATED OR NEW. THE PERFORMANCE OF HVOF
COATED PARTS IMPROVED BY 80-90%.
SILT PROBLEM EXPERIENCED
(PERFORMANCE OF GENERATING UNITS UNDER HIGH SILT LOAD)