
_. __ - ___.. _..... ._ _ _
-
Also, it is very important that the top of the berm for the canal and
forebay be kept at the same elevation as the top of the diversion structure,
because if the penstock were closed,
the water in the canal would seek the
same elevation throughout the intake system (canal, forebay, etc).
If
the
berm in the forebay were lower than the overall water level, the'forebay
would be flooded. If the canal is so long that it is not practical to keep
the berm at the same elevation,
a series of stop logs should be used to
section off the canal.
After sizing the canal,
make a sketch of the cross-sectional area of
the canal. Note the width (WC) and the total depth (dc). The total
depth is the distance from natural ground to the bottom of the canal.
Figure 4.4-6 is a sketch of the example canal.
4.4.2.3 Settling Basin.
A settling basin is recommended for sites'
where the power canal will be l/2 mile or longer.
The purpose of the basin
is to prevent sediment buildup in the power canal. The basin slows the
water down and allows the settlement of the larger material (fine sands,
etc.) to occur in the basin.
Periodically, the basin is flushed out through
a cleanout pipe.
\
A good rule of thumb is to make the basin four times wider than the
power canal, 2 to 3 feet deeper, if possible, and at least 90 feet long
(see Figure 4.4-7).
If
this rule is followed and the power canal is
designed for 2 fps,
then the settling basin velocity will be less than
0.5
fps.
Thus,
wS
= 4 x WC
where
ws =
width of settling basin in feet
WC =
width of canal in feet, from Equation (4.4-3).
4.4-14
(4.4-4)