Release Evaluation Activities
The activities for release evaluation do not need to be performed linearly. Figure
16.4 indicates which activities can be performed concurrently. The list below briefly
describes the activities associated with Step 16, Release Evaluation.
Prepare for the post-implementation review.
All aspects of the completed project are subject to review. That includes
strategies, plans, documents, designs, deliverables, procedures, and
infrastructure. The goal of the review is to get an accounting of what worked
well on the project and what did not, and to produce a list of action items to
implement changes to the development process.
1.
Organize the post-implementation review meeting.
Prepare a list of discussion topics and an agenda, and distribute them to all
attendees. The agenda should list the date, time, place, attendees, and topics
to be discussed. Appoint a facilitator and scribe, and find a venue for the
session.
2.
Conduct the post-implementation review meeting.
The business sponsor should open and close the review session. The project
manager should explain the agenda, the rules of the meeting, and the roles of
the facilitator and the scribe. The scribe should document all discussion points,
which must be reviewed at the end of the session. Assign any action items that
come up during the session.
3.
Follow up on the post-implementation review.
Action items are usually assigned to the attendees, but they can occasionally be
delegated to staff other than the attendees. In either case, someone must
follow up on the action items to ensure that they are performed. Action items
can include updating the standards or the methodology, revising estimating
guidelines, seeking resolution to a business problem, or repairing an urgent
problem that cannot wait for the next release. Prioritize functions or data
dropped from the scope due to constraints on the BI project so you can bundle
them with future releases.
4.
Figure 16.4. Release Evaluation Activities