
stations contain significant design blunders
 and
 that
these mistakes occur
 in
 every conceivable category
including
 hydraulics,
 the
 mechanical system,
 the
 elec-
trical system,
 and
 common sense. Blunders
 are
 expen-
sive
 in
 construction, operation,
 or
 maintenance.
 At
 best,
they
 occasion minor annoyance
 and
 embarrassment.
Make
 yours
 one of the
 elite
 5%
 with sound planning,
forthright
 conferences with clients
 and
 their operators,
periodic design reviews
 and
 design checklists,
 and
thoughtfulness
 and the
 application
 of
 common sense
 to
reduce errors
 and
 omissions
 to an
 acceptable level.
Some decisions
 can be
 reached only
 after
 cost
comparison studies
 are
 made (see Example 29-1),
 but
nearly
 all
 decisions should
 be
 made with
 the
 coordi-
nated
 help
 of
 supporting professionals, whether
 in-
house
 or
 carefully
 selected outside consultants,
 in the
following
 disciplines
 and
 subdisciplines:
•
 Civil engineering
°
 Surveying
°
 Soils
 (or
 geotechnical) engineering
°
 Hydraulics (including transient analysis)
°
 Structural engineering
•
 Mechanical engineering
°
 Heating, ventilating, and/or
 air
 conditioning
°
 Noise
°
 Vibration
°
 Odor control
°
 Pumps
 and
 piping
°
 Engines
•
 Electrical engineering
•
 Instrumentation
 and
 control
•
 Architecture.
The
 project leader must
 be
 able
 to
 communicate with
the
 professionals
 in
 these disciplines,
 and to do so
effectively
 requires familiarity with
 the
 language,
symbols,
 and (to
 some degree)
 the
 problems involved
with
 each discipline.
After
 reaching
 the
 major
 decisions that
 affect
 the
basic design criteria,
 the
 requirements
 of
 each system
must
 be
 clearly conveyed
 to
 each designer.
 The
 duty
 of
the
 project leader
 is to
 coordinate information transfer
between support disciplines
 to
 ensure
 an
 efficient
design
 and an
 economical pumping station devoid
 of
blunders
 caused
 by the
 interference
 of one
 discipline
with
 another.
 The
 importance
 of
 keeping
 a
 complete
and
 legible
 set of
 records
 in, for
 example,
 a
 three-ring
binder cannot
 be
 overemphasized.
 The
 records should
include memoranda
 of
 important conferences
 and
 tele-
phone
 calls,
 design
 memoranda
 to
 individuals
 in
 sup-
port disciplines, design calculations,
 and
 sketches.
 All
records should
 be
 indexed,
 and
 they should
 be
 self-
explanatory
 and
 easily understood because
 (1)
 acci-
dents
 and
 opportunity
 frequently
 change
 the
 comple-
ment
 of an
 office,
 (2)
 design commenced
 by one
engineer
 may
 have
 to be
 completed
 by
 another,
 and (3)
a
 lawsuit
 may
 hinge
 on
 adequate records analyzed
 and
interpreted
 by
 someone other than either author.
Augment
 this chapter with Sections 6-8, 15-1,
16-1,
 the first
 third
 of
 Chapter
 17,
 Sections 22-1
 and
22-2,
 and (as all of
 them apply
 to
 preliminary design)
Chapters
 24, 26, and 27.
 Codes
 and
 standards
 are
identified
 only
 by
 their abbreviations, which
 are
defined
 in
 Appendix
 E.
25-1
 .
 Need
 for
 Pumping
 Stations
Pumping stations
 are
 expensive
 to
 construct, maintain,
and
 operate. They should
 be
 avoided whenever practi-
cal. Consider
 the
 following factors when deciding
whether
 to
 install
 a
 pumping station:
•
 Topography, excavation, elevations,
 and
 capacity
 of
existing water distribution
 and
 treatment systems
 or
sewage
 collection
 and
 treatment systems
•
 Capital,
 operation,
 and
 maintenance costs along
with
 the
 possibility that additional skilled personnel
may
 be
 needed
•
 Problems such
 as
 odor
 or
 noise
 and
 other adverse
aesthetic
 effects.
In
 some circumstances, odor
 control
 may
 represent
the
 major
 cost
 of
 operation.
 In
 1981
 regulatory agen-
cies forced
 the
 owner
 of a
 1.1
 m
3
/s
 (25
 Mgal/d)
 sew-
age
 pumping station
 in
 California
 to
 install
 an
 odor-
control scrubbing system that cost
 $200
 to
 $300/d
 for
operation. Because there
 is no
 scientific
 way to
 evalu-
ate
 odors,
 the
 owner
 and the
 engineer
 may be at the
mercy
 of
 hostile residents.
Possible
 alternatives
 to
 installing
 a
 pumping sta-
tion
 include
 the
 following:
•
 Increasing
 the
 head
 at an
 existing water pumping
station
 by
 changing
 impellers,
 pumps,
 or
 drivers
• A
 reservoir
 at a
 critical elevation that could
 be filled
when
 water demands (and transmission
 losses)
 are
low
• A
 deep,
 gravity-flow
 interceptor sewer, perhaps
installed
 in a
 tunnel
•
 Individual, on-site,
 or
 community underground
sewage
 disposal systems
 at a
 lower elevation, espe-
cially when
 the
 area served
 is
 small.
In
 some situations
 it may be
 desirable
 to
 construct
a
 bare-bones
 design
 for a
 short
 service
 life
 pending
the
 eventual construction
 of a
 long-term (and more
costly) conveyance facility.