
Paper F5: Performance management
236 Go to www.emilewoolfpublishing.com for Q/As, Notes & Study Guides © EWP
Time spent waiting for work due to a bottleneck or hold-up at an earlier stage in
the production process
Running out of a vital direct material, and having to wait for a new delivery of
the materials from a supplier.
A lack of work to do due to a lack of customer orders.
A feature of idle time is that it is recorded, and the hours ‘lost’ due to idle time are
measured.
Sometimes idle time may be an unavoidable feature of the production process, so
that an allowance for idle time is included in the standard cost.
Methods of including idle time in standard costs
There are at least three ways of allowing for idle time in a standard cost.
Method 1. Include idle time as a separate element of the standard cost, so that
the standard cost of idle time is a part of the total standard cost per unit.
Method 2. Allow for a standard amount of idle time in the standard hours per
unit for each product. This is the same approach described above for materials
wastage and standard costing. The standard hours per unit therefore include an
allowance for expected idle time.
Method 3. Allow for the expected idle time by adjusting the standard rate per
hour. This approach has been used in the suggested solutions to an F5
examination question in the past. However, we strongly advise against it,
because idle time is about efficiency and labour time, not the rate per hour paid
to employees. Even so, the technique is illustrated below.
Example
A company manufactures Product X. Due to the nature of the production process,
there is some idle time and it has been estimated that the ‘normal’ amount of idle
time is 10% of hours worked.
Ignoring idle time, the standard time to make 1 unit of Product X is 0.36 hours.
Labour is paid $18 per hour.
This means that the labour time to make 1 unit of product X is 0.36/0.90 = 0.40
hours, of which 0.04 hours are idle time.
There are three ways of making an allowance for in the standard cost the expected
idle time.
Method 1: Include idle time as a separate element of the standard cost. The standard
cost per unit will include the following items:
$
Active hours worked: 0.36 hours × $18 per hour
6.48
Idle time: 0.04 hours × $18 per hour
0.72
7.20