
 
178
  8: Variance analysis  ⏐  Part B  Standard costing 
4.1 Example: variable overhead variances 
Suppose that the variable production overhead cost of product X is as follows. 
2 hours at $1.50 = $3 per unit 
During period 6, 400 units of product X were made. The labour force worked 820 hours, of which 60 hours were 
recorded as idle time. The variable overhead cost was $1,230. 
Calculate the following variances. 
(a)  The variable production overhead total variance 
(b)  The variable production overhead expenditure variance 
(c)  The variable production overhead efficiency variance 
Since this example relates to variable production costs, the total variance is based on actual units of production. (If the 
overhead had been a variable selling cost, the variance would be based on sales volumes.) 
 
  $      
400 units of product X should cost (
×
 $3) 
1,200 
 but did cost
  
1,230
 
Variable production overhead total variance
  
     30
  
(A) 
4.2 Subdividing the variable overhead total variance 
In many variance reporting systems, the variance analysis goes no further, and expenditure and efficiency variances are 
not calculated. However, the adverse variance of $30 may be explained as the sum of two factors. 
(a)  The hourly rate of spending on variable production overheads was higher than it should have been, that is 
there is an 
expenditure variance
. 
(b)  The labour force worked inefficiently, and took longer to make the output than it should have done. This 
means that spending on variable production overhead was higher than it should have been, in other words 
there is an 
efficiency (productivity) variance
. The variable production overhead efficiency variance is 
exactly the same, in hours, as the direct labour efficiency variance, and occurs for the same reasons. 
It is usually assumed that 
variable overheads are incurred during active working hours
, but are not incurred during idle 
time (for example the machines are not running, therefore power is not being consumed, and no direct materials are being 
used). This means in our example that although the labour force was paid for 820 hours, they were actively working for only 
760 of those hours and so variable production overhead spending occurred during 760 hours. 
4.2.1 The variable overhead expenditure variance 
This is the difference between the amount of variable overhead that should have been incurred in the actual hours actively 
worked, and the actual amount of variable overhead incurred. Refer to the data in Section 4.1. 
 
  $      
 
760 hours of variable production overhead should cost ( 
×
 $1.50) 
1,140 
 
but did cost 
 
1,230
 
 
Variable production overhead expenditure variance
  
     90
  
(A) 
4.2.2 The variable overhead efficiency variance 
If you already know the direct labour efficiency variance, the variable overhead efficiency variance is exactly the same in 
hours, but priced at the variable production overhead rate per hour. In the example in Section 4.1, the efficiency variance 
would be as follows. 
199433                                     www.ebooks2000.blogspot.com