ICOLD Bulletin **:  The Specification and Quality Control of Concrete for Dams 
 
Revision 7.0 
25 of 71
 March 2006 
For RCC, lift thickness is normally specified as well as the method for ensuring monolithic 
construction within each lift. The same applies to conventional mass concrete, but here the layer 
thickness within each lift is also specified. To eliminate the risk of segregation at the base of a 
lift, particularly with large MSA and lean mass concrete, a bedding mix with a lesser MSA and 
possibly a higher cementitious content may be required. 
Tests for concrete consistency (slump or VeBe test for RCC) as well as concrete temperature at 
the point of delivery may be required along with acceptance criteria. The acceptance criteria will 
include allowable variations in measured properties and grounds for rejection of concrete as 
unsuitable. 
4.2.2  Inspection 
Control of the concrete placement by inspection is essential to ensure that the required end 
product is achieved. The concrete is normally inspected at the point of delivery to the site and at 
discharge into the form. Inspection is a visual check on the appearance of the concrete where 
workability, uniformity and conformity with established appearance are important. Deviations 
suggest that something is wrong with the mixture and that corrective action is required.  
In some circumstances it may be necessary to adjust the workability of concrete at the placement 
by the addition of water while it is in the transit mixer. This is an acceptable practice providing 
the specified water-cement ratio and the total allowable water in the mix are not exceeded. 
However, this adjustment should not be necessary in a well controlled concrete manufacturing 
process. Unusual loss of workability is commonly a sign of problems in the system or with the 
materials. 
Good communications between the point of placement and the batch plant are essential. Any 
undesired changes in fresh concrete properties at the placement have to be acted upon and 
corrections made to the mixture at the batching and mixing plant.  
Working procedures have to be followed and verified by the inspectors. Important factors are 
correct placement procedures (lift thicknesses, set-backs of successive lifts, elimination of rock 
pockets) and consolidation procedures (depth and time of vibration, uniformity of treatment) and 
conformity of equipment to specification requirements. Verification of the adequacy of the 
curing method and time is important. 
4.2.3  Testing at time of placement 
The purpose of routine control tests is to check and confirm the properties of the fresh concrete 
such as temperature, workability, and air content, and immediately make any adjustments that 
are necessary.  These tests should be run on the first batch out of the plant and randomly during 
each shift or placement or whenever change is observed in the appearance of the concrete.  
Inspectors can quickly learn to visually judge the consistency or workability of the concrete as 
delivered to the placement. These inspectors should be alert to any changes and to notify the 
batching/mixing plant immediately when concrete characteristics are not as they should be. This 
requires effective and reliable communications equipment, either radio or landlines. 
Testing is performed at time of placement to ensure that the concrete has the appropriate 
workability, temperature, compacted density and air content. When delivery to the site is by 
truck, the concrete is commonly tested before it is discharged to avoid the risk of removal of 
non-conforming concrete from the placement. Workability is measured with the slump test for 
conventional mass concrete. For low workability (zero slump RCC) mixes the Loaded VeBe test 
is normally employed (other tests are in use in some countries). The Loaded VeBe time also is 
dependent on the test equipment vibration frequency (function of the site power supply),