ICOLD Bulletin **:  
The Specification and Quality Control of Concrete for Dams
 
 
Revision 7.0 
56 of 71
 March 2006 
 
8.2.5
 
Official reporting 
The test and inspection report distribution diagram is shown in Figure 4. There are two types of 
testing: field and laboratory. Field test occurs during concrete or RCC placement. Field 
technicians perform a series of tests, record the test results, and inform the field inspectors. 
Laboratory tests are performed in the on-site QC laboratory. The Laboratory Manager reviews 
the test data before entering in the computer database. The computer database recalculates and 
stores the test data. The original test data are filed and at the end of the job these documents will 
go to Document Control. At the end of the day, the Laboratory Manager generates reports for the 
inspectors. Every week, the Laboratory Manager generates test reports. The Resident Engineer 
reviews the reports. After reviewing, the reports the reports are distributed to the Project 
Manager, DSOD, the Design Engineer and the Owner.  
When inspector observes that the contractor’s work complies with the project specification, the 
inspector writes a Daily Field Report (DFR). The DFR is then reviewed by the Lead Inspector 
and the Construction Manager. When the inspector observes deviations from the project 
specification, a non-compliance report (NCR) is generated and issued. The non-compliance 
report is distributed to the responsible party for the non-compliance report for evaluation and a 
recommended disposition. The Resident Engineer and Design Engineer review the recommended 
disposition. Upon approval from the Resident Engineer and/or Design Engineer, the Contractor 
conducts the corrective action. The inspectors verify the completion of the corrective action and 
issue a closed NCR. The NCR is reviewed by the Construction Manager, Resident Engineer, 
Project Manager, DSOD, and the Owner.  If the NCR has modified the design documents it is 
then posted as a design change.  
8.2.6
 
Tracking of concrete strength 
Figure 5 shows the chart developed to track the strength of the RCC built into the dam. The chart 
shows that the control of strength at 365-day maturity can be classed as good with a coefficient 
of variation of 12.9%. The results of the tests on specimens subjected to 7-day accelerated cure 
are shown to be a good guide to the 365-day strength. The coefficients of variations increase 
with lesser maturities and this is typical of high fly-ash mixes. 
8.2.7
 
References 
Tarbox, Glenn S., Michael F. Rogers, David E. Kleiner, and Gerard E. Reed, III, 
Olivenhain 
Dam Design, 
Roller-Compacted Concrete For Dams And Dam Rehabilitation, International 
Seminar and Construction Tour, San Diego, California, 2002. 
Ehasz, J., H. Ehrlich, M. Pauletto, J. Reed, K. Steele, and G. McBain, 
Partnering For Success At 
the Olivenhain Dam
, Dams – Innovations for Sustainable Water Resources, 22
nd
 Annual 
USSD Conference, San Diego, California, 2002, p. 389- 397. 
Tarbox, Glenn S., Malcolm Dunstan, Russ Grant, Tom Reynoldson, and James Stiady, 
Supplementary Olivenhain Dam Trial Mix Program,
 Dams – Innovations for Sustainable 
Water Resources, 22
nd
 Annual USSD Conference, San Diego, California, 2002, p. 271- 
285. 
Holderbaum, Rodney., Robert A. Kline, Jr., Michael F. Rogers, Randall J. Hartman, and Russell 
Grant, 
Design of Roller-Compacted Concrete Materials for The Olivenhain Dam
, Dams –