ICOLD Bulletin **:  The Specification and Quality Control of Concrete for Dams 
 
Revision 7.0 
42 of 71
 March 2006 
8.1.4  Concrete Properties: 
Almost eighty percent of the chilled concrete poured in Sardar Sarovar Dam (SSD) is mass 
concrete i.e. A
150
 S
160
 grade (the suffix to A gives the maximum size of aggregate, the suffix to S 
gives the 28-day strength in kg/cm
2
).  Several concrete mix designs for different locations of the 
dam have also been carried out as shown in Table 2 
Concrete samples were collected from the batching and mixing plant and test specimens were 
150 mm dia. x 300mm for compressive strength measurement. For casting specimens with 
75mm or 150 mm MSA., wet screening to remove particles larger than 40 mm was done. For 
every 50,000 m
3 
of mass concrete placed in the dam, cylindrical test specimens of 600mm x 
1200 mm were made without wet screening. These were tested in a 2,000 tonne compression 
testing machine. 
8.1.5  Concrete Production and Placement 
Two concrete manufacturing plants were installed, one on each bank of the river. The left and 
right bank plants had capacities of 5,000 m
3
/d and 3,000 m
3
/d respectively. Each installation 
consisted of a comprehensive aggregate screening plant and batching and mixing plant including 
chilled water plants and ice-makers. The batching of the concrete was computer controlled. The 
left bank installation had four 4.5 m3 drum mixers with a combined output of 330 m
3
/h. The 
right bank installation had two batch plants with a combined output of 240 m
3
/h. 
A cable crane was used to deliver the concrete to the placements in the dam. 
From temperature considerations, all concrete to be placed in the dam, except those components 
where pre-cooled concrete is not envisaged, was to be pre-cooled with a placing temperature not 
more than 13
0
 C. The temperature was measured after concrete was placed and compacted in the 
forms. Concrete was not permitted to be placed at temperature above 15.5 
0
C and then only in 
exceptional circumstances.  
Pneumatic vibrators having a capacity of 150 m
3
 per hour mounted on a backhoe were being 
used for the compaction of concrete. The vibrator had a diameter of 150 mm and a length of 
1.1 m. For one cubic metre of concrete, the time requirement for the compaction was 25 to 30 
seconds. 
Air entrainment was used to enhance wet and hardened concrete properties. The agent was a 
liquid solution prepared in the project laboratory. In a 200 litre drum, 15.48 kg of rosin and 1.62 
kg flaked caustic soda were added to 180 litre warm water. The dosage of air entraining agent 
(AEA) was 150 ml per cubic metre of concrete. The cost of AEA was Rs.0.70 (US$ 0.015) per 
cubic meter of concrete. 
8.1.6  Quality Control System during Dam Construction: 
The Quality Control system comprised the following main activities. 
(i)  Control of production process by inspection of the equipment, particularly the 
concrete plants and the aggregates processing plants. 
(ii)  Control by testing and inspection of the properties of the concrete constituents  
(iii)  Control of concrete batching by inspection of load cells, deviation records, water 
content of fine aggregates and W/C ratio. 
(iv)  Control of fresh concrete sampling and testing. 
(v)  Control of hardened concrete by testing samples and statistical conformity 
analysis.