15  Planning, operation and economics of wind farm projects  493 
-  For variable-speed wind turbines with pitch control the portion of the 
costs of generator and control increase. 
In addition to the production costs, the total wind turbine investment costs include 
share the design and development costs, the profit and further costs attributable to 
warranty, transport and erection.  
The other portions of the total investment costs mentioned in Fig. 15-8 are influ-
enced to a large extent by local site conditions such as the wind farm project size 
(single wind turbine or wind farm), the type of soil and the distance to the grid-
connection point. Therefore, when comparing economically efficient wind farm  
projects of the same size there will always a spreading of the actual project costs 
be observed. 
The grid connection costs are often the second-biggest investment cost factor, 
Fig. 15-8. These vary strongly according to local conditions, i.e. the distance to the 
next grid-connection point, and the requirements of the local grid operator as well. 
The German Renewable Energy Sources Act (EEG) provides an unambiguous 
definition as to whom the costs are to be allocated. Basically, the grid connection 
costs are borne by the wind farm operator.   
However, if the local grid is too weak for the planned wind farm capacity the 
grid reinforcement costs have to be borne by the grid operator who is legally 
obliged to permit wind power feeding. Therefore, the grid reinforcement costs do 
not form part of the investment cost estimation. 
Table 15.3  Cost structure of wind turbine components and assembly , typical values according 
to [4, 5] 
Rated power   600 kW  1,200 kW  Typical span  
Component € Share 
in % 
€ Share
in % 
of cost share 
in % 
Gearbox and coupling  80,400 21.8 115,000 18.1 10 to 25 
Rotor blades  63,800 17.3 150,000 23.6 15 to 25 
Tower (incl. coating)  58,000 15.7 150,000 23.6 12 to 25 
Generator and control   43,800 11.9 65,000 10.2 10 to 20 
Nacelle frame and 
yaw bearing  
31,600 8.6 35,000 5.5 5 to 10 
Hub and main shaft  29,000 7.9 40,000 6.3 5 to 10 
Housing  16,600 4.5 18,000 2.8 2 to 5 
Cables and sensors  13,400 3.6 18,000 2.8 2 to 5 
Hydraulics  11,600 3.1 15,000 2.4 2 to 5 
Yaw system  8,700 2.4 10,000 1.6 1 to 3 
Assembly   11.600 3.1 20,000 3.2 2 to 5 
Total  368,500 100.0 636,000  100.0  
  614 €/W   530 €/kW    
Remark: The total wind turbine investment costs include additionally R&D 
costs, risk, profit, warranty, transport and erection