
432 Electric Power Distribution Handbook
disabled. This practice is done to reduce the damage for a failure of one of
the station exit cables.
The duration of the open interval — the dead time between reclose
attempts — is also a consideration. For a smaller number of reclose attempts,
use longer delays to give tree branches and other material more time to clear.
Operator practices must also be considered as part of the reclosing scheme.
Not uncommonly, an operator manually recloses the circuit breaker after a
feeder lockout (especially during a storm). This sends the breaker or recloser
through its whole reclosing cycle along with all of the bad effects (like more
equipment damage and more voltage sags) with very little chance of success.
Some engineers and field personnel believe that the purpose of the extra
reclose attempts is to burn the fault clear. This is dangerous. Faults regularly
burn clear on low-voltage systems (<480 V), rarely at distribution primary
voltages. Faults can burn clear on primary systems. The most common
example is that tree branches or animals can be burned loose. The problem
with this concept is that, just as easily, the fault burns the primary conductor,
which falls to the ground causing a high-impedance fault. Fires and equip-
ment damage are also more likely with the “burn clear” philosophy.
To reduce the impacts of subsequent reclose attempts, we could switch
back to an instantaneous operation after the first time-overcurrent relay
operation. If the fault does not clear after the first time-overcurrent relay
operation, it means the fault is not downstream of a fuse (or a recloser). The
reason to use a time overcurrent relay is to coordinate with the fuse. Since
the fuse is out of the picture, why not use a faster trip for subsequent reclose
attempts? While not commonly done, we could implement this with digital
relays. The setting of the “subsequent reclose” instantaneous relay element
should be different than the first-shot instantaneous. Set the pickup at the
pickup of the time-overcurrent relay. Because of inrush on subsequent
attempts, we may use a fast time-overcurrent curve or an instantaneous
element with a short delay (something like 5 cycles).
As an example, if a utility uses a 0–15–30–90 sec reclosing cycle, the system
is subjected to five faults if the system goes through its complete cycle. With
the instantaneous operation enabled on the first attempt and disabled on
subsequent attempts, we have a very high total duration of the fault current.
For a CO-11 ground relay with a time-dial of 3, a 2-kA fault clears in roughly
1 sec. For the reclosing cycle to lock out, the system has a total fault time of
4.1 sec (one 0.1-sec fault followed by four 1-sec faults). If the instantaneous
operation is enabled for reclose attempts 2 through 4, the total fault duration
is 1.4 sec (one 0.1-sec fault followed by a 1-sec fault and three 0.1-sec faults).
This greatly reduces the damage done by certain faults.
8.9.2 Immediate Reclose
An immediate reclose (also called an instantaneous or fast reclose) means
having no intentional time delay (or a very short time delay) on the first
1791_book.fm Page 432 Monday, August 4, 2003 3:20 PM
(C) 2004 by CRC Press LLC