water to flow into the suction vessel rather than continue to the pumps
has the effect of further aggravating rates of flow deceleration through a
failing pump thus imposing more severe closure conditions on the pump
discharge check valves.
As the transient progresses it is not uncommon for the head upstream
of the pumps to exceed the downstream head. Then the check valves
will reopen, allowing flow to re-establish and also largely stabilising air
volumes within the vessels. Following flow reversal upstream and down-
stream of the pumping station, the upstream head will start to fall while
downstream head rises. Check valves will then reclose.
In the case of high-lift pumps, the check valves may not reopen if the
head upstream of the pumps does not rise to the minimum level of fall-
ing head in the downstream vessel. In these circumstances the more
rapid closure of the check valves will mean that more water will
enter the upstream vessel and more water will be withdrawn from the
downstream vessel. There will be a tendency for the necessary vessel
volumes to increase above the volumes required where a vessel was
installed only on one side of a pumping station.
As with a pressure vessel located on the downstream side of a pump-
ing station, throttling of flow can also be applied to the upstream vessel.
This throttling action may be applied either during inflow to the vessel
or to the outflow depending upon a need to suppress the upsurge on the
suction side (throtting of inflow) or the downsurge (throtting of out-
flow).
A pressure vessel may also be used as part of an overall protection
package. It can be used to prolong the time taken for piezometric
level to fall, at the start of a main, to a sufficient extent that no
unacceptably low pressures are developed between downstream points
on the main where other forms of protection are present.
Appendix Equations for estimating air vessel parameters
When a detailed hydraulic transient analysis of a pipeline system has
been commissioned and the time and costs associated with constructing
an accurate model have been covered then it is not so important to
have an initial estimate of pressure vessel characteristics. In other
instances, for instance where a tender is being prepared and a sum is
to be included for pressure transient protection, it is useful to be able
to price the pressure vessel installation as accurately as possible.
Should the contract not be awarded, any expense may not be recover-
able and so analysis time should be as brief as possible. The use of design
200
Pressure transients in water engineering