
flow when a specific slope is available. The exact rela-
tionship depends on the canal profile used, but an appro-
ximate formula is
If the area’s topography indicates a larger average slope
between the intake on the stream and the forebay than
that required, a similar procedure can be followed. In
this case, the larger slope implies that a smaller and
therefore less expensive canal would be necessary but
that the velocity would be greater. This may make it
necessary to line the canal, which would increase its
cost. Another approach is to maintain the original slope
and use canal drops where appropriate (see Drop struc-
tures, p. 110).
Fzcavation
Before work can proceed, it is necessary to lay out the
alignment or route of the canal. After the canal
centerline and right-of-way limits have been staked, all
vegetation along the canal alignment or route should
then be stripped from the surface and removed. Strip-
ping should be deep enough to remove all roots and
organic matter, because they prevent proper compac-
tion of the soil and can introduce earthworm and rodent
activity.
The canal should be excavated in original subsoil. To
avoicl future settling, it should not be built over filled-in
areas. Settling can cause cracks in any lining; with an
unlined canal, it can change the canal gradient and
thereby cause overspilling of the banks. Inadequate of
cotnpaction of the soil may also increase the water’s
rate infiltration into the ground, which in turn may
adversely affect the integrity of an unlined canal or a
canal with cracked lining. It is often preferable to use a
properly supported flume (p. 112) over a dip in the ter-
rain rather than to build over a filled-in area.
Excavation should be neat and LS close to the desired
profile as possible (Fig. 5.74). Wooden templates can
facilitate the task for larger canals. For grade and
alignment between grade stakes, a string line should be
used. Over-cutting during excavation should be avoided,
because it requires extra time and effort to backfill and
properly compact this fill, or if the canal is to be lined,
extra material would be required for the lining.
The subsoil excavated from the canal can be used to
build up the bank. The top of the bank should be wide
enough io ensure stability, prevent excessive seepage,
and facilitate maintenance. It shollld equal or exceed
the design flow depth in the canal but not be less than
about 30 cm.
If it is necessary to fill in a slight dip and the original
subsoil is dry, the surface should be scarified (loosened)
to a depth of about 5 cm and moistened to ensure that it
bonds with the fill material. Fill should be added in
approximately 7 cm layers over the sea to be filled and
then compacted manually or mechanically.
Fig. 5.74. Excavation
should
be carefully undertaken
to
the
desired
profile.
At this site, concrete
sills rather than
grade stakes have been
placed at 4
m
interwls. A 4 m
length of square steel channeling spanning these sills will
be
used as
a reference for placing a stone-masonry lining
CI t the base of
the canal.
Soil material used for fill should be selected from out-
side the canal right-of-way. It should be moi,jt and uni-
form, have as many fine par+-.:les as possible (silt or
clay), and be free of stones, roots, sticks, and organic
matter. Moisture in soil is necessary for proper com-
paction. It acts as a lubricant to allow soii particles to
slide closer together when tamped. The proper amount
of water can be judged by taking a handful of soil, ball-
ing it up in the hand with a good grip like a firm hand-
shake, and releasing the pressure. The soil must remain
in a ball. Optimum compaction is obtained with 12%-
15% moisture by weight, depending on soil type. Com-
paction is adequate when a heel print with a person’s
full weight upon it will not indent the fill over 0.3 mm
(17).
canal lining
For centuries, numerous countries have used unlined
earth canals for conveying water for irrigation. These
are also frequently used with micro-hydropower
schemes because:
o they are easily built and maintained by unskilled per-
sonnel,
o they require no special equipment or material, and
o their initial cost is low.
Occasionally, it may be necessary to line a canal with
104 Civil works