the rising water, which may cause excess deflection. However, sufficient
backfill must be placed over the pipe (about 3 ft) to prevent flotation of the
pipe.
Design I. Use a select clean sand or gravel backfill material (class II; Table 3.9)
for bedding, haunching, and initial backfill compacted to 85 percent standard
Proctor density. From Table 3.9, long-term deflection will be about 3 percent (see
Chap. 3 for additional discussion on the use of Table 3.9).
Design II. Use a select silty-sandy gravel backfill material (class III;
Table 3.9) for bedding, haunching, and initial backfill compacted to
85 percent standard Proctor density. From Table 3.9, long-term
deflection will be 3.5 percent.
Note: These deflections are substantially lower than the allowed 7.5 percent
long-term deflection. However, because of the wet condition and the rela-
tively deep cover soil, density in the pipe zone must not be less than the den-
sity at the critical void ratio. This density is often around 90 percent of
Proctor density. For added safety, 90 percent density is recommended. Also
design I is preferred to design II because in wet trench conditions, the com-
paction of class III backfill is more difficult.
Example 7.3—A 27-in gravity sewer pipe A 27-in SDR 35, PS 46, PVC
sewer pipe is to be installed 15 ft deep. The soil is clay, except in most areas
there is some basalt rock which must be blasted. What type of soil embed-
ment system will be required for this installation?
1. Pipe must not be laid directly on hardpan, bedrock, or any sharp stones
with dimensions larger than 1
1
2
in and preferably no stones larger than
3
4
in.
2. Excavate at least 6 in below grade, and prepare a firm uniform bedding
of crushed, well-graded stone.
3. Select haunching and initial backfill material: Consider class I, class II,
class III, or class IV materials as listed in Table 3.9. A Proctor density of
80 percent is sufficient for either class II or class III soils. Class IV soils
are often overlooked as pipe embedment materials, but could be used if
the trench is not wet and the soil is compacted to 85 percent Proctor den-
sity. Of course, class I soil will also meet design requirements (y/D
7.5 percent).
4. Spangler’s method could also be used, but it is not required.
5. Pipe should not be placed directly on sharp rock outcroppings. Also, large
sharp blasted basalt rock should not be placed directly against the pipe.
(A select imported material is recommended.)
Example 7.4—A 48-in ribbed PVC pipe A 48-in ribbed PVC pipe is to be
installed 20 ft deep. The native soil is fine sand with traces of silt and clay.
The pipe stiffness of the ribbed pipe is 10 lb/in
2
. For a special design the
owner has requested that this pipe be installed such that the maximum ver-
tical deflection does not exceed 3 percent. Also, to keep costs down, he would
396 Chapter Seven